|
Work is moving along on the new Person County Schools bus
garage, with May 1 targeted as the completion date.
Person County Board of Education Chairman Gordon Powell said
Monday that work was progressing nicely on the project, despite
an initial setback of nearly a month due to state Department
of Insurance delays.
The slab for the bus garage was poured last Thursday, Powell
said, and work was taking place this week on the slab for
the fuel station, which requires a separate pad and fuel tank
enclosures.
Powell said the rain on Sunday may have delayed the work
for a day or so, but that overall, work is going OK.
He said the contractor had told him that steel erection for
the bus garage building should begin this week.
I dont know if the rain will hamper that,
Powell said, but the delay, if there is one, should last for
only one or two days.
He said that a large percentage of this thing [project]
is the floor. Thats the hard part. The concrete
slab had to be poured, said Powell, and fitted with plumbing
and electrical before work on the metal and brick structure
could begin.
The erection of the building and work on the brick façade
should move along at a fairly good pace, Powell said, barring
any weather delays between now and May.
In October, Larry King, director of Environmental Services
for the school system, told Powell and the other members of
the school board that the Department of Insurance in Raleigh
had delayed the beginning of the project due to a few minor
questions.
The contractor for the project, E.M. Wilkerson & Sons,
could not obtain a building permit until the Department of
Insurance gave its approval. This week, Powell said the delay
had put the work three to four weeks behind.
When the project is complete, it will signify the end of
a six-year quest to replace the aging bus garage on Leasburg
Road. For the past several years, student transportation workers
have been unable to drive todays large buses into the
bays at the old garage.
|